CV (Cost Variance) | EV - AC (earned value - actual cost) |
SV (Schedule Variance) | EV - PV (earned value - planned value) |
CPI (Cost Performance Index) | EV / AC (earned value divided by actual cost) |
EAC (Estimate at Completion) | BAC / CPI (budget at completion divided by cost performance index) |
ETC (Estimate to Complete) | EAC - AC (Estimate at Completion - Actual Cost) |
VAC (Variance at Completion) | BAC - EAC (Budget at Completion - Estimate at Completion) |
PERT | (P + 4M + O) / 6 |
Standard Deviation of Activity | (P - O) / 6 |
Variance of an Activity | [ ( P - O) / 6 ] squared (standard deviation squared) |
Total float | LS - ES or LF - EF |
EAC (Estimate at Completion -2) | AC + ETC (actual cost plus estimate to complete) |
EAC (Estimate at Complete - typical variance) | AC + (BAC - EV) (actual cost plus the total of budget at completion minus earned value) |
EAC (Eastimate at Completion 4) | AC +( (BAC-EV)/CPI ) |
Cumulative CPI | EV (cume) - AC (cume) |
Present Value (PV) | FV / (1 + r) to the n-th power |
Communication Channels | [N * (N-1) ] / 2 |