Flashcards: PMP Formulas

About these flashcards

Created by:

karenfarnham on December 18, 2009

Subjects:

project management

Description:

Formulas for pmp exam

Groups:

PMP / PM Study, PMP Study 2012

Log in to favorite or report as inappropriate.
Pop out
No Messages

You must log in to discuss this set.

Flashcards: PMP Formulas

CV (Cost Variance)
EV - AC (earned value - actual cost)
1/16

Study:

Speller

Learn

Test

Play Games:

Scatter

Space Race

Terms

Definitions

CV (Cost Variance) EV - AC (earned value - actual cost)
SV (Schedule Variance) EV - PV (earned value - planned value)
CPI (Cost Performance Index) EV / AC (earned value divided by actual cost)
EAC (Estimate at Completion) BAC / CPI (budget at completion divided by cost performance index)
ETC (Estimate to Complete) EAC - AC (Estimate at Completion - Actual Cost)
VAC (Variance at Completion) BAC - EAC (Budget at Completion - Estimate at Completion)
PERT (P + 4M + O) / 6
Standard Deviation of Activity (P - O) / 6
Variance of an Activity [ ( P - O) / 6 ] squared (standard deviation squared)
Total float LS - ES or LF - EF
EAC (Estimate at Completion -2) AC + ETC (actual cost plus estimate to complete)
EAC (Estimate at Complete - typical variance) AC + (BAC - EV) (actual cost plus the total of budget at completion minus earned value)
EAC (Eastimate at Completion 4) AC +( (BAC-EV)/CPI )
Cumulative CPI EV (cume) - AC (cume)
Present Value (PV) FV / (1 + r) to the n-th power
Communication Channels [N * (N-1) ] / 2

Set Champions

Scatter Champion

33.2 secs by harrise007

Completed “Learn” mode

plg2831