Set: Project Management Ch 7, 9, 10

Familiarize

Learn

Test

Play Scatter

Play Space Race

Voice Scatter

Voice Race

Combine with other sets Login to add to Favorites
Print: Term List | Flashcards Editing not allowed
Export Deleting not allowed

Share these flash cards

With group: None
HTML link to set: Tiny link:
Share on Facebook Share on MySpace

All 20 terms

TermDefinition
learning ratethe percentage of the previous worker hours per unit required for doubling the output
variationsthe pattern of deviations in costs and usage used for exception reporting to management
program budgetingaggregating income and expenditures by project or program, often in addition to aggregation by organizational unit or activity
fast-trackingoverlapping the design and build phases of a project
heuristica formal process for solving a problem, like a rule of thumb, that results in an acceptable solution
negativeif the slope is _______ (positive or negative), as the time required to complete a project or task is decreased, the cost is increased
CV=EV-AC
SV=EV-PV
TV=ST-AT
CPI=EV/AC
SPI=EV/PV
TPI=ST/AT
CSI=(CPI)(SPI)
ETC=(BAC-EV)/CPI
EAC=ETC+AC
computer paralysisexcessive fascination or activity with the computer rather than the project itself such that the project suffers
earned valuean approach for monitoring project progress that relies on the budgeted cost of activities completed to ascribe value
cost variancethe budgeted cost of the work performed less the actual cost of the work performed
schedule variancethe budgeted cost of work completed less the budgeted cost of work scheduled at this time
time variancethe scheduled time for the work completed less the actual time

Set Information

Terms 20
Creator shane_reiser
Created April 11, 2007
Groups None
Subject pm
Access Anyone
Edit Creator Only
Get rid of ads on Quizlet

Description

Quiz questions based on chapters 7, 9, and 10 of "Project Management: A Managerial Approach" by Meredith and Mantel. Sixth Edition

Pop out

Discuss

No Messages
Last Message: never

You must be logged in to discuss this set.

Top Users

  1. shane_reiser - 28 scores

Most Missed Words

  1. TPI =ST/AT - 2 misses
  2. ETC =(BAC-EV)/CPI - 2 misses
  3. computer paralysis excessive fascination or activity with the computer rather than the project itself such that the project suffers - 2 misses
  4. SPI =EV/PV - 1 miss
  5. heuristic a formal process for solving a problem, like a rule of thumb, that results in an acceptable solution - 1 miss