Rita's Process Chart

About this set

Created by:

tedunni  on February 6, 2008

Subjects:

process, pmp, charg

Description:

Project Management Process Chart

Classes:

PMP Study 2012

Log in to favorite or report as inappropriate.
Pop out
Last Message: 13 months ago
xoksx : This is not complete. it have to be 79 terms
xoksx : http://quizlet.com/3255529/ritas-process-chart-flash-cards/
smyarber : this is the old chart. update to 6th edition

You must log in to discuss this set.

Rita's Process Chart

Initiating
Select Project Manager
1/72
Preview our new flashcards mode!

Study:

Cards

Speller

Learn

Test

Scatter

Games:

Scatter

Space Race

Tools:

Export

Copy

Combine

Embed

Order by

Terms

Definitions

Initiating Select Project Manager
Initiating Determine company culture and existing systems
Initiating "Collect processes, procedures and historical information"
Initiating Divide large project into phases
Initiating Identify stakeholders
Initiating Document business needs
Initiating Determine project objectives
Initiating Document assumptions and constraints
Initiating Develop project charter
Initiating Develop preliminary scope statement
Planning Determine how you will do planning - part of management plans
Planning Create project scope statement
Planning Determine team
Planning Create WBS and WBS dictionary
Planning Create activity list
Planning Create network diagram
Planning Estimate resource requirements
Planning Estimate time and cost
Planning Determine critical path
Planning Develop schedule
Planning Develop budget
Planning "Determine quality standards, processes and metrics"
Planning Determine roles and responsibilities
Planning Determine communications requirements
Planning "Risk identification, qualitative and quantitative risk analysis and response planning"
Planning Iterations - go back
Planning Determine what to purchase
Planning Prepare procurement documents
Planning "Finalize the "how to execute and control" aspects of all management plans"
Planning Create process improvement plan
Planning Develop final PM plan and performance measurement baselines
Planning Gain formal approval for plan
Planning Hold kickoff meeting
Executing Acquire final team
Executing Execute the PM plan
Executing Work to produce product scope
Executing Recommend changes and corrective actions
Executing Send and receive information
Executing "Implement approved changes, defect repair, preventive and corrective actions"
Executing Continuous improvement
Executing Follow processes
Executing Team building
Executing Give recognition and rewards
Executing Hold progress meetings
Executing Use work authorization system
Executing Request seller responses
Executing Select sellers
Monitoring and Controlling Measure against the performance measurement baselines
Monitoring and Controlling Measure according to the management plans
Monitoring and Controlling Determine variances and if they warrant corrective action or a change
Monitoring and Controlling Scope verification
Monitoring and Controlling Configuration management
Monitoring and Controlling "Recommend changes, defect repair, preventive and corrective actions"
Monitoring and Controlling Integrated change control
Monitoring and Controlling "Approve changes, defect repair, preventive and corrective actions"
Monitoring and Controlling Risk audits
Monitoring and Controlling Manage reserves
Monitoring and Controlling Use issue logs
Monitoring and Controlling Facilitate conflict resolution
Monitoring and Controlling Measure team member performance
Monitoring and Controlling Report on performance
Monitoring and Controlling Create forecasts
Monitoring and Controlling Administer contracts
Closing Develop closure procedures
Closing Complete contract closure
Closing Confirm work is done to requirements
Closing Gain formal acceptance of the product
Closing Final performance reporting
Closing Index and archive records
Closing Update lessons learned knowledge base
Closing Hand off completed product
Closing Release resources

First Time Here?

Welcome to Quizlet, a fun, free place to study. Try these flashcards, find others to study, or make your own.

Set Champions

Scatter Champion

16.4 secs by anandhbl 

Space Race Champion

161,880 points by virgilio_avila 

Speller Champion

97.3% correct by markgro