According to PMBOK

Develop Project Charter

KA: Integration
The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

Develop Project Management Plan

KA: Integration
The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The project's integrated baselines and subsidiary plans may be included within the project management plan.

Direct and Manage Project Work

KA: Integration
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project's objectives.

Monitor and Control Project Work

KA: Integration
The process of tracking, reviewing, and reporting project progress against the performance objectives defined in the project management plan.

Perform Integrated Change Control

KA: Integration
The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition.

Close Project or Phase

KA: Integration
The process of finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project.

Plan Scope Management

KA: Scope
The process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled

Collect Requirements

KA: Scope
The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives...

Define Scope

KA: Scope
The process of developing a detailed description of the project and product...

Create WBS

KA: Scope
The process of subdividing project deliverables and project work into smaller, more manageable components

Validate Scope

KA: Scope
The process of formalizing acceptance of the completed project deliverables

Control Scope

KA: Scope
The process of monitoring the status of the project and product scope and managing changes to the scope baseline

Plan Schedule Management

KA: Time
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule

Define Activities

KA: Time
The process of identifying documenting the specific actions to be performed to produce the project deliverables

Sequence Activities

KA: Time
The process of identifying and documenting relationships among the project activities

Estimate Activity Resources

KA: Time
The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity...

Estimate Activity Durations

KA: Time
The process of estimating the number of work periods needed to complete individual activities with estimated resources

Develop Schedule

KA: Time
The process of analyzing activity sequences, durations, resource requirements, and schedule contraints to create the project schedule model...

Control Schedule

KA: Time
The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan...

Plan Cost Management

KA: Cost
The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs

Estimate Cost

KA: Cost
The process of developing an approximation of the monetary resources needed to complete project activities

Determine Budget

KA: Cost
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

Control Costs

KA: Cost
The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline. *Tracking the actual work according to the budget to see if any adjustments need to be made.

Please allow access to your computer’s microphone to use Voice Recording.

Having trouble? Click here for help.

We can’t access your microphone!

Click the icon above to update your browser permissions above and try again

Example:

Reload the page to try again!

Reload

Press Cmd-0 to reset your zoom

Press Ctrl-0 to reset your zoom

It looks like your browser might be zoomed in or out. Your browser needs to be zoomed to a normal size to record audio.

Please upgrade Flash or install Chrome
to use Voice Recording.

For more help, see our troubleshooting page.

Your microphone is muted

For help fixing this issue, see this FAQ.

Star this term

You can study starred terms together

NEW! Voice Recording

Create Set