31 terms

PMP Chapter 6 Project Time Management

STUDY
PLAY
Project Time Management
the processes required to manage timely completion of the project (p129)
Define Activities
the process of identifying the specific actions to be performed to produce the project deliverables (p 129)
Sequence Activities
the process of identify and documenting relationships among the project activities (p 129)
Estimate Activity Resources
the process of estimating the type and quality of materials, people, equipment, or supplies required to perform each activity (p 129)
Estimate Activity Durations
the process of approximating the number of work periods needed to complete individual activities with estimated resources (p 129)
Develop Schedule
the process of analyzing activity sequence, durations, resources requirements, and schedule constraints to create the project schedule (p 129)
Control Schedule
the process of monitoring the status of the project progress and managing changes to the schedule baseline (p 129)
Name the inputs of the Define Activities Process
1. Scope Baseline
2. Enterprise Environmental Factors
3. Organizational Process Assets
Name the tool/techniques of the Define Activities Process
1. Decomposition
2. Rolling Wave Planning
3. Templates
4. Expert Judgement
Name the outputs of the Define Activities Process
1. Activity List
2. Activity Attributes
3. Milestone List
Name the inputs of the Sequence Activities Process
1. Activity List
2. Activity Attributes
3. Milestone List
4. Project Scope Statement
5. Organizational Process Assets
Name the tools/techniques of the Sequence Activities Process
1. Precedence diagramming method (PDM)
2. Dependency determination
3. Applying leads and lags
4. Schedule network templates
Name the outputs of the Sequence Activities Process
1. Project Schedule Network
2. Project document updates
Name the inputs of the Estimate Activity Resources Process
1. Activity List
2. Activity Attributes
3. Resource Calendar
4. Enterprise Environmental Factors
5. Organizational Process Assets
Name the tools/techniques of the Estimate Activity Resources Process
1. Expert Judgement
2. Alternatives Analysis
3. Published Estimating Data
4. Bottom-up Estimating
5. Project Management Software
Name the outputs of the Estimate Activity Resources Process
1. Activity resource requirements
2. Resource breakdown structure
3. Project Document Updates
Name the inputs of the Estimate Activity Durations process
1. Activity List
2. Activity Attributes
3. Activity Resource Requirements
4. Resource Calendars
5. Project Scope Statement
6. Enterprise Environmental Factors
7. Organizational process assets
Name the tools/techniques of the Estimate Activity Durations process
1. Expert judgement
2. Analogous estimating
3. Parametric Estimating
4. Three-Point estimating
5. Reserve Analysis
Name the outputs of the Estimate Activity Durations Process
1. Activity Duration Estimates
2. Project Document Updates
Name the inputs of the Develop Schedule Process
1. Activity List
2. Activity Attributes
3. Project Schedule Network Diagrams
4. Activity Resources Requirements
5. Resource Calendars
6. Activity Duration Estimates
7. Project Scope Statement
8. Enterprise Environmental Factors
9. Organizational Process Assets
Name tools/techniques of the Develop Schedule Process
1. Schedule Network Analysis
2. Critical path method
3. Critical chain method
4. Resource leveling
5. What-if scenario analysis
6. Applying leads and lags
7. Schedule Compression
8. Scheduling tool
Name outputs of the the Develop Schedule Process
1. Project Schedule
2. Schedule Baseline
3. Schedule Data
4. Project Document Updates
Name the inputs of the Control Schedule Process
1 Project Management Plan
2 Project Work Schedule
3 Work Performance Information
4 Organizational Process Assets
Name the tool/techniques of the Control Schedule Process
1 Performance Reviews
2 Variance Analysis
3 Project Management Software
4 Resource leveling
5 What-if Scenario analysis
6 Adjusting leads and lags
7 Schedule Compression
8 Scheduling tool
Name the outputs of the Control Schedule Process
1 Work performance measurements
2 Organizational process assets updates
3 Change requests
4 Project Management Plan Updates
5 Project Document Updates
Activity
work packages are typically decomposed into smaller components, that represent the work necessary to complete the work package (p 133)
Decomposition
a technique that involves subdividing the project work package into smaller, more manageable components called activities (p 134)
Rolling Wave Planning
a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS (p 135)
Activity List
a comprehensive list including all schedule activities required on the project
Precedence Diagramming Method (PDM)
a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles (nodes) to represent activities, and connects them with arrows that show the logical relationships that exist between them. (p 138)
Mandatory Dependencies
dependencies that are contractually required or inherent in the nature of the work (p 139)