71 terms

In/output 2 of 2

STUDY
PLAY
What are tools and techniques from the Plan Quality processes in the Planning process group?
1. Design of experiments 2. Cost-benefit analysis 3. Cost of quality 4. Benchmarking 5. Statistical sampling 6. Flowcharting 7. Proprietary quality management methodologies 8. Additional quality planning tools 9. Control charts
What are outputs from the Plan Quality processes in the Planning process group?
1. Project document updates 2. Quality management plan 3. Quality metrics 4. Quality checklists 5. Process improvement plan
What are inputs from the Plan Risk Management processes in the Planning process group?
1. Organizational process assets 2. Enterprise environmental factors 3. Communication management plan 4. Schedule management plan 5. Cost management plan 6. Project scope statement
What are tools and techniques from the Plan Risk Management processes in the Planning process group?
1. Planning meetings and analysis
What are outputs from the Plan Risk Management processes in the Planning process group?
1. Risk management plan
What are inputs to the Plan Risk Responses processes in the Planning process group?
1. Risk management plan 2. Risk register
What are tools and techniques to the Plan Risk Responses processes in the Planning process group?
1. Expert judgment 2. Contingent response strategies 3. Strategies for positive risks or opportunities 4. Strategies for negative risks or threats
What are outputs to the Plan Risk Responses processes in the Planning process group?
1. Project document updates 2. Project management plan updates 3. Risk-related contract decisions 4. Risk register updates
What are inputs to the Sequence Activities processes in the Planning process group?
1. Organizational process assets 2. Project scope statement 3. Milestone list 4. Activity attributes 5. Activity list
What are tools and techniques to the Sequence Activities processes in the Planning process group?
1. Schedule network templates 2. Applying leads and lags 3. Dependency determination 4. Precedence diagramming method
What are outputs to the Sequence Activities processes in the Planning process group?
1. Project document updates 2. Project schedule network diagrams
What are inputs to the Acquire Project Team process in the Executing process group?
1. Organizational process assets 2. Project management plan
What are tools and techniques to the Acquire Project Team process in the Executing process group?
1. Virtual teams 2. Acquisition 3. Negotiation 4. Pre-assignment
What are outputs to the Acquire Project Team process in the Executing process group?
1. Project management plan updates 2. Resource calendars 3. Project staff assignments
What are outputs to the Administer Procurements process in the Executing process group?
1. Project management plan 2. Contract 3. Performance reports 4. Approved change requests 5. Work performance information 6. Procurement documents
What are tools and techniques to the Administer Procurements process in the Executing process group?
1. Performance reporting 2. Contract change control system 3. Inspections and audits 4. Payment systems 5. Claims administration 6. Records management system 7. Procurement performance reviews
What are outputs to the Administer Procurements process in the Executing process group?
1. Project management plan updates 2. Procurement documentation 3. Organizational process assets updates 4. Change requests
What are inputs to the Close Procurements process in the Executing process group?
1. Procurement documentation 2. Project management plan
What are tools and techniques to the Close Procurements process in the Executing process group?
1. Records management system 2. Negotiated settlements 3. Procurement audits
What are outputs to the Close Procurements process in the Executing process group?
1. Organizational process assets updates 2. Closed procurements
What are inputs to the Develop Project team process in the Executing process group?
1. Resource calendars 2. Project management plan 3. Project staff assignments
What are tools and techniques to the Develop Project team process in the Executing process group?
1. Project staff assignments 2. Recognition and rewards 3. Co-location 4. Ground rules 5. Team-building activities 6. Training 7. Interpersonal skills
What are outputs to the Develop Project team process in the Executing process group?
1. Enterprise environmental factors updates 2. Team performance assessments
What are inputs to Direct and Manage Project Execution process in the Executing process group?
1. Organizational process assets 2. Enterprise environmental factors 3. Approved change requests 4. Project management plan
What are tools and techniques to Direct and Manage Project Execution process in the Executing process group?
1. Project management information system 2. Expert judgment
What are outputs to Direct and Manage Project Execution process in the Executing process group?
1. Project document updates 2. Project management plan updates 3. Work performance information 4. Deliverables
What are inputs to Perform Quality Assurance process in the Executing process group?
1. Quality control measurements 2. Work performance information 3. Quality metrics 4. Project management plan
What are tools and techniques to Perform Quality Assurance process in the Executing process group?
1. Process analysis 2. Quality audits 3. Plan quality and perform quality control tools and techniques
What are outputs to Perform Quality Assurance process in the Executing process group?
1. Project document updates 2. Project management plan updates 3. Change requests 4. Organizational process assets updates
What are inputs to the Plan Communications process in the Executing process group?
1. Organizational process assets 2. Enterprise environmental factors 3. Stakeholder management strategy 4. Stakeholder register
What are the tools and techniques to the Plan Communications process in the Executing process group?
1. Communication methods 2. Communication models 3. Communication technology 4. Communication requirements analysis
What are outputs to the Plan Communications process in the Executing process group?
1. Project document updates 2. Communication management plan
What are Inputs to the Control Costs process in the Monitor and Controlling group?
1. Project funding requirements 2. Work performance information 3. Organizational process assets 4. Project management plan
What are tools and techniques to the Control Costs process in the Monitor and Controlling group?
1. Variance analysis 2. Earned value management 3. Forecasting 4. Performance reviews 5. Project management software 6. To-complete performance index (TCPI)
What are outputs to the Control Costs process in the Monitor and Controlling group?
1. Project document updates 2. Work performance measurements 3. Budget forecasts 4. Organizational process assets 5. Change requests 6. Project management plan
What are inputs to the Control Schedule process in the Monitor and Controlling group?
1. Project schedule 2. Work performance information 3. Organizational process assets 4. Project management plan
What are tools and techniques to the Control Schedule process in the Monitor and Controlling group?
1. Schedule compression 2. Performance reviews 3. Variance analysis 4. Project management estimating software 5. What-if scenario analysis 6. Adjusting leads and lags 7. Scheduling tool 8. Resource leveling
What are outputs to the Control Schedule process in the Monitor and Controlling group?
1. Project document updates 2. Work performance measurements 3. Organizational process assets 4. Change requests 5. Project management plan updates
What are inputs to the Control Scope process in the Monitor and Controlling group?
1. Organizational process assets 2. Requirements traceability matrix 3. Requirements documentation 4. Work performance information 5. Project management plan
What are tools and techniques to the Control Scope process in the Monitor and Controlling group?
1. Variance analysis
What are outputs to the Control Scope process in the Monitor and Controlling group?
1. Project document updates 2. Project management plan updates 3. Change requests 4. Organizational process assets updates 5. Work performance measurements
What are inputs to the Distribute Information process in the Monitor and Controlling group?
1. Organizational process assets 2. Performance reports 3. Project management plan
What are tools and techniques to the Distribute Information process in the Monitor and Controlling group?
1. Information distribution tools 2. Communication methods
What are outputs to the Distribute Information process in the Monitor and Controlling group?
1. Organizational process assets updates
What are inputs to the Manage Project Team process in the Monitor and Controlling group?
1. Organizational process assets 2. Performance reports 3. Team performance assessments 4. Project management plan 5. Project staff assignments
What are tools and techniques to the Manage Project Team process in the Monitor and Controlling group?
1. Interpersonal skills 2. Issue log 3. Conflict management 4. Project performance appraisals 5. Observation and conversation
What are outputs to the Manage Project Team process in the Monitor and Controlling group?
1. Project management plan updates 2. Change requests 3. Organizational process assets updates 4. Enterprise environmental factors updates
What are inputs to the Manage Stakeholder Expectations process in the Monitor and Controlling group?
1. Organizational process assets 2. Change log 3. Issue log 4. Project management plan 5. Stakeholder management strategy 6. Stakeholder analysis
What are tools and techniques to the Manage Stakeholder Expectations process in the Monitor and Controlling group?
1. Management skills 2. Interpersonal skills 3. Communication methods
What are outputs to the Manage Stakeholder Expectations process in the Monitor and Controlling group?
1. Project document updates 2. Project management plan updates 3. Change requests 4. Organizational process assets updates
What are inputo the Manage Stakeholder Expectations Monitor and Control Project Work process in the Monitor and Controlling group?
1. Organizational process assets 2. Enterprise environmental factors 3. Performance reports 4. Project management plan
What are Tools & Techniques to the Monitor and Control Project Work process in the Monitor and Controlling group?
1. Expert judgment
What are outputs to the Monitor and Control Project Work process in the Monitor and Controlling group?
1. Project document updates2. Project management plan updates3. Change requests
What are inputs to the Monitor and Control Risks process in the Monitor and Controlling group
1. Performance reporting 2. Work performance information 3. Project management plan 4. Risk register
What are tools and techniques to the Monitor and Control Risks process in the Monitor and Controlling group
1. Status meetings 2. Reserve analysis 3. Technical performance measurement 4. Variance and trend analysis 5. Risk audits 6. Risk assessment
What are outputs to the Monitor and Control Risks process in the Monitor and Controlling group
1. Project document updates 2. Project management plan updates 3. Change requests 4. Risk register updates
What are inputs to the perform integrated change control process in the Monitor and Controlling group
1. Organizational process assets 2. Enterprise environmental factors 3. Change requests 4. Work performance information 5. Project management plan
What are tools and techniques to the perform integrated change control process in the Monitor and Controlling group
1. Change control meetings 2. Expert judgment
What are outputs to the perform integrated change control process in the Monitor and Controlling group
1. Project document updates 2. Project management plan updates 3. Change request status updates
What are inputs to the perform quality control process in the Monitor and Controlling group
1. Quality metrics 2. Quality checklists 3. Work performance measurements 4. Approved change requests 5. Deliverables 6. Organizational process assets 7. Project management plan
What are the tools and techniques to the perform quality control process in the Monitor and Controlling group
1. Run chart 2. Cause and effect diagrams 3. Control charts 4. Flowcharting 5. Pareto chart 6. Scatter diagram 7. Statistical sampling 8. Inspection 9. Approved change requests review 10. Histogram
What are outputs to the perform quality control process in the Monitor and Controlling group
1. Project document updates 2. Quality control measurements 3. Validated changes 4. Organizational process assets updates 5. Change requests 6. Project management plan updates
What are inputs to the Report Performance process in the Monitor and Controlling group
1. Organizational process assets 2. Budget forecasts 3. Work performance measurements 4. Work performance information 5. Project management plan
What are tools and techniques to the Report Performance process in the Monitor and Controlling group
1. Reporting systems 2. Communication methods 3. Forecasting methods 4. Variance analysis
What are outputs to the Report Performance process in the Monitor and Controlling group
1. Change requests 2. Organizational process assets updates 3. Performance reports
What are inputs to the Verify Scope process in the Monitor and Controlling group
1. Validated deliverables 2. Requirements traceability matrix 3. Requirements documentation 4. Project management plan
What are tools and techniques to the Verify Scope process in the Monitor and Controlling group
1. Inspection
What are outputs to the Verify Scope process in the Monitor and Controlling group
1. Project document updates 2. Change requests 3. Accepted deliverables
What are inputs to the Closing process in the Closing group
1. Organizational process assets 2. Accepted deliverables 3. Project management plan
What are Tools and Techniques to the Closing process in the Closing group
1. Expert judgment
What are outputs to the Closing process in the Closing group
1. Organizational process assets updates 2. Final product, service, or result transition