Search
Browse
Create
Log in
Sign up
Log in
Sign up
Upgrade to remove ads
Only $2.99/month
PMP Formulas
STUDY
Flashcards
Learn
Write
Spell
Test
PLAY
Match
Gravity
Terms in this set (15)
No. of Communication Channels
n (n-1)/2
n = number of members in the team
n = should include the project manager
e.g. if the no. of team members increase from 4 to 5, the increase in communication channels: 5(5-1)/2 - 4(4-1)/2 = 4
Schedule Performance Index (SPI)
SPI = EV/PV
EV = Earned Value
PV = Planned Value
< 1 behind schedule
= 1 on schedule
> 1 ahead of schedule
Cost Performance Index (CPI)
CPI = EV/AC
EV = Earned Value
AC = Actual Cost
< 1 Over budget
= 1 On budget
> 1 Under budget
sometimes the term 'cumulative CPI' would be shown, which actually is the CPI up to that moment
Schedule Variance (SV)
SV = EV - PV
EV = Earned Value
PV = Planned Value
< 0 Behind schedule
= 0 On schedule
> 0 Ahead of schedule
Cost Variance (CV)
CV = EV - AC
EV = Earned Value
AC = Actual Cost
< 0 Over budget
= 0 On budget
> 0 Within budget
Estimate at Completion (EAC) if original is flawed
"EAC = AC + New ETC
AC = Actual Cost
New ETC = New Estimate to Completion
if the original estimate is based on wrong data/assumptions or circumstances have changed
Estimate at Completion (EAC) if BAC remains the same
EAC = AC + BAC - EV
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
the variance is caused by a onetime event and is not likely to happen again
Estimate at Completion (EAC) if CPI remains the same
EAC = BAC/CPI
BAC = Budget at completion
CPI = Cost performance index
if the CPI would remain the same till end of project, i.e. the original estimation is not accurate
Estimate at Completion (EAC) if substandard performance continues
EAC = AC + (BAC - EV)/(CPI*SPI)
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index
use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used
To-Complete Performance Index (TCPI)
TCPI = (BAC - EV) / (BAC - AC)
BAC = Budget at completion
EV = Earned value
AC = Actual Cost
TCPI = Remaining Work /Remaining Funds
BAC = Budget at completion
EV = Earned value
CPI = Cost performance index
< 1 Under budget
= 1 On budget
> 1 Over budget
Estimate to Completion
ETC = EAC -AC
EAC = Estimate at Completion
AC = Actual Cost
Variance at Completion
VAC = BAC - EAC
BAC = Budget at completion
EAC = Estimate at Completion
< 0 Under budget
= 0 On budget
> 0 Over budget
PERT Estimation
(O + 4M + P)/6
O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate
Standard Deviation
(P - O)/6
O= Optimistic estimate
P= Pessimistic estimate
this is a rough estimate for the standard deviation
Float/Slack
LS - ES
LS = Late start
ES = Early start
LF - EF
LF = Late finish
EF = Early finish
= 0 On critical path
< 0 Behind schedule
THIS SET IS OFTEN IN FOLDERS WITH...
PMP
1,547 terms
PMP Formulas
71 terms
PMP Formulas
16 terms
Names to know PMP Cert
16 terms
YOU MIGHT ALSO LIKE...
PMP Formulas
16 terms
Earned Value Abbreviations
12 terms
PMP Study - Part 14 - Controlling Cost
54 terms
EARNED VALUE
21 terms
OTHER SETS BY THIS CREATOR
PMI Lexicon of Project Management Terms
145 terms
English
66 terms
OTHER QUIZLET SETS
AP Macro Unit 4
80 terms
us history final: questions
62 terms
Chap 15 Gender and Leadership
13 terms
Chapter 5 Mental Health Assessment
85 terms