A consultant is working on a Service Cloud implementation with a fixed budget and timeline. The analysis phase of the project has just been completed. Additional requirements were discovered that will result in the project exceeding timeline and budget constraints. What is the first step the consultant should take to address the issue?
A. Adjust the dates in the project plan to account for the additional requirements and communicate the new timeline.
B. Add development resources to the project team to build out the additional requirements.
C. Adjust the project scope to accommodate new requirements and continue with the original project schedule
D. Document the requirements gap and communicate development options to the project team
A. Adjust the dates in the project plan to account for the additional requirements and communicate the new timeline.
B. Add development resources to the project team to build out the additional requirements.
C. Adjust the project scope to accommodate new requirements and continue with the original project schedule
D. Document the requirements gap and communicate development options to the project team