8 terms

Ops Midterm 1

STUDY
PLAY
Activity time
how long it takes to work on a TASK
Capacity
(1/activity time) how many units worker can make in 1 unit of time
Bottleneck
process step w/ lowest capacity
Flow rate
min (D, process capacity)
demand or capacity constrained?
Utilization
(Rate/Capacity)
Little's Law
I = RT (Flow Rate Flow Time)
Flow Time
time t start from finish on the process
Activity time + wait time
labor utilization
labor content / (productive + idle time per 1 flow unit)