Which of the following is the process of monitoring the status of the project to update the project schedule and manage changes to the schedule?
Click the card to flip 👆
Control schedule
Click the card to flip 👆
1 / 265
1 / 265
Flashcards
Learn
Test
Match
Q-Chat
Created by
Nicole_Albanese3
Share
Share
Students also viewed
Stakeholder (CAPM)
37 terms
CAPM Exam
Teacher
196 terms
BA 101 chapters 6-10 test
146 terms
Cost (CAPM)
61 terms
Chapter 4: Ethical and Sustainable Sourcing
42 terms
Certified Associate Project Manager (CAPM) Prep
145 terms
ITIL Chapter 3
31 terms
ACCTMIS 4500 Exam 2 (SG, PC, RS)]
64 terms
Terms in this set (265)
Which of the following is the process of monitoring the status of the project to update the project schedule and manage changes to the schedule?
Control schedule
Risk transference nearly often involves:
Payment of a risk premium to the party taking on the risk
The interaction of the various system components creates the organizational culture and capabilities that are important for the project. Which role is typically responsible for establishing the system?:
Organization's management
Which of the following is the process of translating the quality management plan into executable quality activities that incorporate the organization's quality policies into the project?:
Manage quality
You are observing and checking the progress and quality of project stakeholder relationships and adjusting strategies and plans for engaging stakeholders. This is known as:
Monitor stakeholder engagement
What is the wbs typically used for?:
To organize and define the total scope of the project
Which of the following is a process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected?:
Change control
What is a work breakdown structure (WBS)?:
A hierarchical decomposition of the total scope of work to be carried out to accomplish the project objectives and create the required deliverables
All of the following are inputs to manage project knowledge except:
Knowledge management?
Culture is a personality characteristic or trait that includes which of the following components?:
Values, norms, and beliefs
What is an input of plan scope management?:
Quality management plan
All of the following are outputs to close project or phase except:
EEFs
A change control board (CCB) is:
A formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project
Which of the following is an output of control procurements, the requirements for which are usually defined in the terms and conditions of the contract and are included in the procurement management plan?:
Closed procurements
Which of the following contract types are used when the requirements are well defined and no significant changes to the scope are expected?:
Fixed-price contracts