You are correct, the answer is A.

A. Testing and releasing a pilot with reduced functionality reduces risk in a number of ways. Reduced functionality should result in fewer overall test cases to run and defects to fix and retest, and in less regression testing. A pilot release made available to a select group of users will reduce the risk associated with a full implementation. All of the benefits of releasing the system to the full user population will not be realized, but some benefits should start to flow. Additionally, some useful comments from real users should be obtained to guide what extra functionality and other improvements need to be included in a full release.

B. When testing starts, a significant amount of defects is likely to exist. Focusing only on the highest-severity functional defects runs the risk that other important aspects such as usability problems and nonfunctional requirements of performance and security will be ignored. The system may go live, but users may struggle to use the system as intended to realize business benefits.

C. Eliminating testing by development is usually a bad idea. Before system acceptance testing begins, some prior testing should occur to establish that the system is ready to proceed to acceptance evaluation. If prior testing by the development team does not occur, there is a considerable risk that the software will have a significant amount of low-level defects, such as transactions that cause the system to hang and unintelligible error messages. This can prove frustrating for users or testers tasked with acceptance testing and, ultimately, could cause the overall test time to increase rather than decrease.

D. The use of a defect tracking tool could help in improving test efficiency, but it does not address the fundamental risk caused by reducing the testing effort on a system in which quality is uncertain. Given the build problems experienced, there is reason to suspect that quality problems could exist.
You are correct, the answer is D.

A. The accuracy of data used in the test environment is not of significant concern as long as these data are representative of the production environment.

B. Using production data in the test environment would not cause test results to be inaccurate. If anything, using production data would improve the accuracy of testing processes because the data would most closely mirror the production environment. In spite of that fact, the risk of data disclosure or unauthorized access in the test environment is still significant and, as a result, production data should not be used in the test environment. This is especially important in a health care organization where patient data confidentiality is critical and privacy laws in many countries impose strict penalties on misuse of these data.

C. Hardware in the test environment should mirror the production environment to ensure that testing is reliable. However, this does not relate to the risk from using live data in a test environment. This is not the correct answer because it does not relate to the risk presented in the scenario.

D. In many cases, the test environment is not configured with the same access controls that are enabled in the production environment. For example, programmers may have privileged access to the test environment (for testing), but not to the production environment. If the test environment does not have adequate access control, the production data are subject to risk of unauthorized access and/or data disclosure. This is the most significant risk of the choices listed.
You are correct, the answer is C.

A. Parallel operation provides a high level of assurance that the new system functions properly compared to the old system. Parallel operation is generally expensive and would not provide a cost savings over most other testing approaches. In many cases, parallel operation is the most expensive form of system testing due to the need for dual data entry, dual sets of hardware, dual maintenance and dual backups—it is twice the amount of work as running a production system and, therefore, costs more time and money.

B. Hardware compatibility should be determined and tested much earlier in the conversion project and is not an advantage of parallel operation. Compatibility is generally determined based on the application's published specifications and on system testing in a lab environment. Parallel operation is designed to test the application's effectiveness and integrity of application data, not hardware compatibility. In general, hardware compatibility relates more to the operating system level than to a particular application. While new hardware in a system conversion must be tested under a real production load, this can be done without parallel systems.

C. Parallel operation is designed to provide assurance that a new system meets its functional requirements. This is the safest form of system conversion testing because, if the new system fails, the old system is still available for production use. In addition, this form of testing allows the application developers and administrators to simultaneously run operational tasks (batch jobs, backups) on both systems to ensure that the new system is reliable before unplugging the old system.

D. Increased resiliency during parallel processing is a legitimate outcome from this scenario, but the advantage it provides is temporary and minor, so this is not the correct answer.
You answered C. The correct answer is D.

A. The capability maturity model (CMM) places heavy emphasis on predefined formal processes and formal project management and software development deliverables, while agile software development projects, by contrast, rely on refinement of process as dictated by the particular needs of the project and team dynamics.

B. Task-level tracking is not used because daily meetings identify challenges and impediments to the project.

C. Agile projects make use of suitable development tools; however, tools are not seen as the primary means of achieving productivity. Team harmony, effective communications and collective ability to solve challenges are of greater importance.

D. A key tenet of the agile approach to software project management is ongoing team learning to refine project management and software development processes as the project progresses. One of the best ways to achieve this is that the team considers and documents what worked well and what could have worked better at the end of each iteration and identifies improvements to be implemented in subsequent iterations. Additionally, less importance is placed on formal paper-based deliverables, with the preference being effective informal communication within the team and with key outside contributors. Agile projects produce releasable software in short iterations, typically ranging from four to eight weeks. This, in itself, instills considerable performance discipline within the team. This, combined with short daily meetings to agree on what the team is doing and the identification of any impediments, renders task-level tracking against a schedule redundant.