What are the processes included in Project Integration Management?
Click the card to flip 👆
4.1 Develop Project Charter, 4.2 Develop Project Management Plan, 4.3 Direct and Manage Project Work, 4.4 Manage Project Knowledge, 4.5 Monitor and Control Project Work, 4.6 Perform Integrated Change Control, and 4.7 Close Project or Phase.
Click the card to flip 👆
1 / 56
1 / 56
Flashcards
Learn
Test
Match
Q-Chat
Created by
jlou7777
Share
Share
Terms in this set (56)
What are the processes included in Project Integration Management?
4.1 Develop Project Charter, 4.2 Develop Project Management Plan, 4.3 Direct and Manage Project Work, 4.4 Manage Project Knowledge, 4.5 Monitor and Control Project Work, 4.6 Perform Integrated Change Control, and 4.7 Close Project or Phase.
The major processes of Project Communications Management are:
Plan Communications Management, Manage Communications, and Monitor Communications
What are the tools and techniques included in the Monitor Stakeholder Engagement process?
Data analysis, decision making, data representation, communication skills, interpersonal and team skills, meetings
What are the inputs to the control scope process?
Project management plan, project documents, work performance data, organizational process assets
What input to the control costs process contains data on project status such as which costs have been authorized, incurred, invoiced, and paid?
Work performance data