Terms in this set (12)
PMO Types
Supportive, Controlling, Directive
PERT Formula
(P + 4M + O) ÷ 6
Crashing
Adding resources
Fast Tracking
Schedule compression (run in parallel)
Qualitative Risk Analysis
Prioritizes risks
Quantitative Risk Analysis
Adds values to risk
Parametric Estimating
Uses datasets to estimate
Top-Down (Analogous) Estimating
High-Level Estimate
Bottom-Up Estimating
Break down and add back up to estimate
Conflict Resolution Strategies
Avoiding/withdrawing.
Smoothing.
Competing/coercing.
Cooperating/accommodating.
Compromising/negotiating.
Collaborating.
Types of Dependencies between activities
Mandatory, discretionary, internal, external
Push vs. pull communication
Sent out vs posted
Sets found in the same folder
Process Groups and Knowledge Areas
43 terms
EVM Formulas
12 terms
Other sets by this creator
Pump Ops
42 terms
Chest Injuries
7 terms
Trauma Assessment
3 terms
Gynecologic Emergencies
3 terms