AIA A101
Flashcards
Learn
Test
Match
Get a hint
What are the different articles in the AIA A101?
Article 1:
Article 2:
Article 3:
Article 4:
Article 5:
Article 6:
Article 7:
Article 8:
Article 9:
Click the card to flip 👆
Article 1: The Contract Documents
Article 2: The Work
Article 3: Date of Commencement and Substantial Completion
Article 4: Contract Sum
Article 5: Payments
Article 6: Dispute Resolution
Article 7: Termination or Suspension
Article 8: Miscellaneous Provisions
Article 9: Contract Documents
Click the card to flip 👆
1 / 10
1 / 10
Flashcards
Learn
Test
Match
Created by
mcr2195
Share
Share
Terms in this set (10)
What are the different articles in the AIA A101?
Article 1:
Article 2:
Article 3:
Article 4:
Article 5:
Article 6:
Article 7:
Article 8:
Article 9:
Article 1: The Contract Documents
Article 2: The Work
Article 3: Date of Commencement and Substantial Completion
Article 4: Contract Sum
Article 5: Payments
Article 6: Dispute Resolution
Article 7: Termination or Suspension
Article 8: Miscellaneous Provisions
Article 9: Contract Documents
AIA A101
Article 1: The Contract Documents
- Contract documents include: drawings, specifications, and addenda
AIA A101
Article 2: The Work
- Work is described by the contract documents
AIA A101
Article 3: Date of Commencement and Substantial Completion
- Dates are binding
- If contractor fails to meet substantial completion date without fault from other parties, damages may be assessed
AIA A101
Article 4: Contract Sum
- Contract sum is "Stipulated Sum", a fixed fee subject to modifications from: alternates, allowances, unit prices, or liquidated damages
- Other payment methods available based on project delivery method