A part structure, lead time (weeks), and on-hand quantities for product are shown in Figure 14.14. From the information shown, generate:
Net requirements for each part to produce 10 As in week 8 using lot-for-lot.
Solution
VerifiedAnswered 11 months ago
Answered 11 months ago
Step 1
1 of 7In this problem, we will be constructing a net material requirements plan.