Question

Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed.

Setup cost =$20=\$ 20

Annual holding cost of mainshaft assembly =$250=\$ 250 per unit

Daily production =300=300 mainshafts

Annual usage =20,000(=50=20,000(=50 weeks ×5\times 5 days each xx daily usage of 80 mainshafts)

Lead time =3=3 days

Safety stock =12=\frac{1}{2} day's production of mainshafts

Solution

Verified
Answered 1 year ago
Answered 1 year ago
Step 1
1 of 12

In this problem, we will solve for the kanban size and the number of kanbans needed.

Create a free account to view solutions

Create a free account to view solutions

Recommended textbook solutions

Operations Management: Sustainability and Supply Chain Management 12th Edition by Barry Render, Chuck Munson, Jay Heizer

Operations Management: Sustainability and Supply Chain Management

12th EditionISBN: 9780134163451 (9 more)Barry Render, Chuck Munson, Jay Heizer
1,698 solutions
Business Management for the IB Diploma Coursebook 2nd Edition by Alex Smith, Peter Stimpson

Business Management for the IB Diploma Coursebook

2nd EditionISBN: 9781107464377Alex Smith, Peter Stimpson
1,183 solutions
Information Technology Project Management: Providing Measurable Organizational Value 5th Edition by Jack T. Marchewka

Information Technology Project Management: Providing Measurable Organizational Value

5th EditionISBN: 9781118898208Jack T. Marchewka
346 solutions
Human Resource Management 15th Edition by John David Jackson, Patricia Meglich, Robert Mathis, Sean Valentine

Human Resource Management

15th EditionISBN: 9781337520164John David Jackson, Patricia Meglich, Robert Mathis, Sean Valentine
249 solutions

More related questions

1/4

1/7