Tej Dhakar's company wants to establish kanbans to feed a newly established work cell. The following data have been provided. How many kanbans are needed?

Daily demand 250 units
Lead time 12\frac 12day
Safety stock 14\frac 14day
Kanban size 50 units

Solutions

Verified
Answered 1 year ago
Step 1
1 of 8

For this problem, we are tasked to identify how many Kanbans are needed to feed a newly established work cell of Tej Dhakar’s Company.