The advantage a Precedence diagram has over a Gantt chart is:

  • its difficulty in depicting networks.
  • its ability to reveal relationships among activities.
  • its complexity its simplicity its lack of riskiness

Solution

Verified
Answered 5 months ago
Answered 5 months ago

A Precedence diagram is a project management tool chart that presents a project schedule on a timeline. It maps out tasks and their dependencies and duration.

Gantt chart is also similar to a precedence diagram in that it is a project management tool that creates a schedule on a timeline. It assigns and sets tasks with their duration that are presented in chronological order.

However, one of the advantages of a Precedence over a Gantt is that it reveals relationships among activities.

Create an account to view solutions

By signing up, you accept Quizlet's Terms of Service and Privacy Policy
Continue with GoogleContinue with Facebook

Create an account to view solutions

By signing up, you accept Quizlet's Terms of Service and Privacy Policy
Continue with GoogleContinue with Facebook

More related questions

1/4

1/7