The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers.
JOB | DATE JOB RECEIVED | PRODUCTION DAYS NEEDED | DATE JOB DUE |
---|---|---|---|
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Which dispatching rule has the best score for utilization metric?
DISPATCHING RULE | JOB SEQUENCE | FLOW TIME | UTILIZATION METRIC | AVERAGE NUMBER OF JOBS | AVERAGE LATENESS |
---|---|---|---|---|---|
EDD | |||||
SPT | |||||
LPT | |||||
FCFS |
Solution
VerifiedAnswered 1 year ago
Answered 1 year ago
Step 1
1 of 5In this problem, we will analyze which among the rules has the best results in terms of utilization metric.
Create an account to view solutions
By signing up, you accept Quizlet's Terms of Service and Privacy Policy
Create an account to view solutions
By signing up, you accept Quizlet's Terms of Service and Privacy Policy
Recommended textbook solutions

Operations Management: Sustainability and Supply Chain Management
12th Edition•ISBN: 9780134163451 (9 more)Barry Render, Chuck Munson, Jay Heizer1,698 solutions

Business Management for the IB Diploma Coursebook
2nd Edition•ISBN: 9781107464377Alex Smith, Peter Stimpson1,183 solutions

Information Technology Project Management: Providing Measurable Organizational Value
5th Edition•ISBN: 9781118898208Jack T. Marchewka346 solutions

Human Resource Management
15th Edition•ISBN: 9781337520164John David Jackson, Patricia Meglich, Robert Mathis, Sean Valentine249 solutions
More related questions
1/4
1/7