The Global Tea and Organic Juice companies have merged. The following information has been collected for the “Consolidation Project.
-
Compute the expected time for each activity.
-
Compute the variance for each activity.
-
Compute the expected project duration.
-
What is the probability of completing the project by day 112? Within 116 days?
-
What is the probability of completing “Negotiate with Unions” by day 90?
Activity | Description | Predecessor | opt | ml | pess |
---|---|---|---|---|---|
Codify accounts | None | ||||
File articles of unification | None | ||||
Unify price and credit policy | None | ||||
Unify personnel policies | None | ||||
Unify data processing | |||||
Train accounting staff | |||||
Pilot run data processing | 18 | ||||
Calculate P & L and balance sheet | , | ||||
Transfer real property | |||||
Train salesforce | |||||
Negotiate with unions | |||||
Determine capital needs | |||||
Explain personnel policies | |||||
Secure line of credit | , | ||||
End |
Solution
VerifiedAnswered 2 years ago
Answered 2 years ago
Step 1
1 of 6The given case revolves around identifying the probability of a project getting completed.
Create a free account to view solutions
By signing up, you accept Quizlet's Terms of Service and Privacy Policy
Create a free account to view solutions
By signing up, you accept Quizlet's Terms of Service and Privacy Policy
Recommended textbook solutions

Project Management: The Managerial Process
6th Edition•ISBN: 9780078096594Clifford Gray, Erik Larson303 solutions

Operations Management: Sustainability and Supply Chain Management
12th Edition•ISBN: 9780134163451 (9 more)Barry Render, Chuck Munson, Jay Heizer1,698 solutions

Business Management for the IB Diploma Coursebook
2nd Edition•ISBN: 9781107464377Alex Smith, Peter Stimpson1,183 solutions

Human Resource Management
15th Edition•ISBN: 9781337520164John David Jackson, Patricia Meglich, Robert Mathis, Sean Valentine249 solutions
More related questions
1/4
1/7